The three storey building in Redlands Lane, Fareham, is built in an arc around landscaped gardens on the site of a former dairy. The project also includes six assisted living bungalows, also set out in an arc. 

Thin Joint construction was used to ensure construction of this 80 bedroom care home could be completed within a 60-week construction programme.

Principle Contractor: The Highwood Group
Client: Gracewell Healthcare
Project:  Parker Meadows Care Home
Project Value:  £4,2 million
Build Method: Thin Joint aircrete construction
Location: Redlands Lane, Fareham, Hampshire
Type of contract:  Design and build
Architect: PDP Architecture
Aircrete contractor: Champion Brickwork
Build time: Total build time from start on site was just 60 weeks